21 October 2026
CfDs are long-term contracts between a low carbon electricity generator and the Low Carbon Contracts Company (LCCC). This Scheme concerns the latest CfD allocation round (AR8).
The scheme is open to applications from any eligible renewable electricity generator with a project in Great Britain with technologies that meet certain size and type requirements.
There is no set maximum subsidy, however bids must fit within the budget. During the allocation process a budget notice will be published specifying the overall budget available for each delivery year applicable to the allocation round, and the administrative strike prices for AR8.
Our key takeaways from the Subsidy Advice Unit (SAU) report are:
- When discussing proportionality, assessments should consider the size of subsidies under the scheme relative to the value of the affected market, or to an estimate of the investment needed to achieve the policy objective.
- When considering whether the design of the Scheme minimises distortions to competition and investment, detail should be included on:
- the rationale for any structure which separates technologies into different auction pots with separate clearing price outcomes;
- why any reduction in bidder participation from the proposed eligibility restrictions is expected to have limited effects on competitive outcomes; and
- whether any hybrid metering arrangements may give rise to broader competition concerns.
- Assessments should consider in detail the effects of the subsidies given under the scheme on market structure and market concentration, and on other comparable organisations.