21 October 2026
This subsidy award is valued at £64 million to Associated British Ports (“ABP”) to support a portion of the £106 million of developmental expenditure. This will include funding the design, environmental assessment, and consenting activities required (progressing ABP’s Future Port Talbot project to a consent ready position). The aim is to develop Port Talbot into one where floating offshore wind (“FLOW”) platforms can be assembled and deployed in the Celtic Sea.
Our key takeaways from the Subsidy Advice Unit (SAU) report are:
- Assessments should describe and evidence the market failure it wishes to address, provide detailed explanations of factors that contribute to the identified coordination failure, and set out how the Subsidy will address (if applicable) any concerns in relation to the equity objective.
- Assessments should explain and evidence how the Subsidy will change economic behaviour and evidence that it will enable future activity that would not have occurred without the Subsidy.
- Assessments should clearly describe and evidence the specific policy objective of the Subsidy, demonstrate that other ways of achieving this have been considered, and evidence why a subsidy is the most appropriate option.
- Furthermore, assessments should clearly and specifically set out what is considered to be the most likely outcome in the absence of the Subsidy.
- Assessments should address in detail the likelihood of other, in this case, ports being able to provide the facilities required to support FLOW deployment. Additionally, it should be explicitly addressed why DESNZ considers compensating ABP for costs already incurred is compliant with the additionality principle.
- Assessments should outline in-depth how the grant intensity was determined, and why the Subsidy is considered proportionate and the minimum necessary to achieve its policy objective (in line with Statutory Guidance), by providing sufficient detail on the negotiation process and the level of due diligence conducted.
- Assessments should demonstrate and evidence the Subsidy’s effects and how its design features help minimise any negative effects of the Scheme on competition and investment in the UK, for example subsidising multiple beneficiaries and why this may or may not be an appropriate approach.
- Assessments should clearly set out potential positive and negative effects of the subsidy in relation to the policy objectives, its geographic impacts and they should conduct a balancing exercise between both in line with the Statutory Guide. They should demonstrate how the Subsidy will deliver benefits over and above what would have happened in the counterfactual scenario and ensure these benefits relate to the specific policy objective, only consider benefits relating to the specific policy objective identified under Principle A, clearly differentiate between direct and long-term benefits and reflect this in the balancing exercise, and consider the potential implications for international trade and investment, focusing in particular on nearby non‑UK ports that may represent competitive alternatives to Port Talbot.
- Assessment should clearly explain and evidence how the Subsidy complies with the energy and environment principles.