23 April 2025
In a landmark step for the UK’s energy strategy, Ofgem has officially opened the first application window under its new cap and floor regulatory scheme for Long Duration Electricity Storage (“LDES”) projects.
This announcement follows the joint publication by Ofgem and the Government of the Technical Decision Document (the “TDD”) in March 2025 on a cap and floor regime to support the deployment of LDES projects capable of delivering greater system resilience and decarbonisation at scale.
What is LDES?
LDES – or Long Duration Electricity Storage – refers to technologies and systems designed to store electrical energy for extended periods, typically ranging from several hours to days. The stored energy can then be dispatched during times of high demand or low renewable output, helping to reduce reliance on fossil fuels while supporting a more secure, affordable, and low-carbon energy system. These storage systems play a critical role in balancing energy supply and demand, integrating renewable energy sources like wind and solar, and ensuring grid stability.
LDES assets will typically be treated as generation assets (requiring a licence) and comprise the following technologies:
- pumped hydro storage;
- thermal energy storage;
- compressed air energy storage; and
- flow batteries and other advanced battery systems.
LDES plays a key part in the Government’s Clean Power 2030 Action Plan, which envisions a significant role for long duration storage in delivering a low-cost, low-carbon energy system.
What is the cap and floor scheme?
The cap and floor scheme is a financial mechanism aimed at encouraging investment in energy storage projects in the UK. This regulatory framework was first introduced by Ofgem in 2014 in respect of electricity interconnectors. Although the regime for LDES includes similar concepts to that for interconnectors, it has been tailored to ensure it is effective for LDES deployment.
The intent of the cap and floor model is to unlock investment in storage technology that may not currently be viable through market revenues alone, while also protecting consumers from excessive payments. The scheme provides revenue certainty to developers of LDES projects by setting a minimum (floor) and maximum (cap) level for revenues, ensuring stability while safeguarding consumer interests.
This works to create a balanced approach to risk and reward sharing. If a project’s revenues fall below the floor, consumers will top up the developer’s income to the agreed floor level. Conversely, if revenues exceed the cap, the surplus will be returned to consumers.
LDES assets will be subject to the scheme for 25 years. While Ofgem may consider requests from developers for shorter terms, such proposals must not be for a period less than 20 years. The rationale relates to the recovery of capital costs for the project: a shorter duration would likely result in higher ‘floor’ levels needing greater consumer support as the costs are stretched over a shorter term.
How is the cap and floor scheme funded?
Funding for the cap and floor scheme will be raised through network charges on electricity system users. Payments to or from LDES licensees will be managed through the National Energy System Operator (NESO) and regulated by Ofgem to ensure compliance and alignment with system needs.
It is not yet clear which specific network charges will be used to fund the scheme for LDES. However, it is expected that such funding may be raised via Transmission Network Use of System Charges (TNUoS) and/or Balancing Services and Use of System Charges (BSUoS).
For example, the regime for electricity interconnectors is funded through TNUoS. If revenues exceed the cap, the surplus is returned to consumers via reduced TNUoS charges; if revenues fall below the floor, consumers top up revenues through increased TNUoS charges.
The Government will legislate for the delivery of the LDES cap and floor scheme, including to confirm the use of network charges in the event a cap or floor is triggered, via the Planning and Infrastructure Bill which was introduced to Parliament on 11 March 2025.
Who can apply?
Ofgem is welcoming applications from developers of eligible LDES projects that can be delivered by either 2030 and 2033. Eligibility will be assessed in a first phase of evaluation by Ofgem in accordance with the Eligibility Criteria Assessment Framework. We set out an outline of the assessment stages below.
At a high level, to be eligible LDES projects must – in addition to other eligibility criteria described below (namely in relation to deliverability, grid connection offer, planning consent, and technological readiness) – have a storage duration of at least 8 hours and meet the minimum size thresholds of either 100MW (stream 1) or 50MW (stream 2).
The LDES cap and floor scheme is also available for significant refurbishments or expansions. As such, provided the refurbishment or expansion project adds an amount of capacity that meets the eligibility criteria, developers undertaking such projects may also apply. In this context, only the cost of the new capacity resulting from the refurbishment or expansion can be supported by the cap and floor scheme.
How does the application process work?
The application process begins with an eligibility assessment to determine whether LDES projects qualify for the cap and floor scheme. Projects that pass this initial stage will proceed to a detailed evaluation phase, which includes a project cost benefit analysis (“CBA”) stage.
This approach largely mirrors that for electricity interconnectors. However, it has been streamlined to enable faster decision-making on cap and floor levels, supporting developers in progressing their financing arrangements more quickly.
In Q2 2026, Ofgem will also offer a limited opportunity for developers to submit updated cost information through a targeted reassessment process to ensure that final cap and floor levels reflect the most accurate and mature estimates available.
The final stage is the post construction review (“PCR”), anticipated to run from 2029, at which point the final cap and floor levels are determined.