It is almost inevitable that large scale developments will be spatially phased in their build out. Flexibility to accommodate a degree of change is needed to enable larger schemes to proceed in a timely manner. A “drop in” permission, making changes to one part of the larger original development site, is one of the tools used to accommodate a larger scheme’s evolution over time. Going forward, the practical use of such applications will be dependent on an interpretation of the base line of the original planning permission.
In November 2020 the Hillside[1] Court of Appeal judgment (subsequent appeal to the Supreme Court dismissed) held that a planning permission should be seen and implemented in full as an integrated whole, and that the implementation of a subsequent ‘drop-in’ permission on part of the site could render any wider planning permission previous granted as unimplementable in its entirety.
The Fiske 2[2] Court of Appeal case in December 2023 explains that the planning system does not preclude several applications for planning permission being made for different developments on the same site. The developer needs to address any physical impossibility/inconsistencies (the long established “Pilkington” principle affirmed in Hillside) and consider how best to de-risk a site where there may be two (or a series of) planning permissions.
In January 2024 the High Court case of R (Dennis) v LB Southwark[3] considered the implications of the Hillside Supreme Court judgment on a major phased outline planning permission and looked at what makes a planning permission severable i.e. capable of then being dealt with in phases. The case involved a phase of the regeneration of the Aylesbury Estate (south of the Elephant and Castle, London) The key Dennis findings are:
The Dennis judgment indicates that for a planning permission to be considered ‘severable’, the subsequent drop-in application itself needs to include an assessment (including in an Environment Statement, if one is required) of individual and discrete development elements on the overall scheme.
Applying all this case law to the facts of an individual large scheme, possibly already under construction in a spatially phased manner, isn’t necessarily easy. Let’s look at a scenario and the issues raised applying the case law:
Let’s imagine the situation where a singular outline planning permission (“the original PP”) has been granted for a scheme proposing a new primary school and new residential. There is a phasing plan (showing different plots/areas) of housing and a location specifically for the new school. Neither the planning conditions or supporting documents nor the description of the development are worded to suggest the school and housing are severable parts. The planning committee report gave no consideration to the ability to sever different phases when the committee resolved to grant the scheme. Subsequent to the first housing units being constructed under the permission it is agreed by the local education authority that a new school is no longer required to accommodate the child yield generated from the new residential units to be provided on site. There is no intention to build the new school and the developer makes a further stand-alone application for planning permission for a community centre and some additional housing (“the School PP”) to be carried out in the area shown in the original PP as the school site.
Issues to be considered
Here are some of the legal issues and questions that arise:
Additional points to note for large developments:
Finally let’s not forgot the many other considerations and implications that need to be looked into, when changes to large schemes are afoot. These include (but are not limited to), CIL charges and when payments are due, modification of s106 obligations to apply to phases, wording of planning conditions requiring discharge and scope for legal challenge of subsequent permissions granted.
Post-election, will the Government bring into force the new section 73B TCPA (in the Levelling up and Regeneration Act 2023) that allows for changes to a planning permission that are not substantially different from the existing permission?[5].This will no doubt be the subject of debate and the scope of the new section, if introduced, could lead to further consideration by the courts. How effective introducing this section would be in practice is one to watch. It surely has limitations for how different/flexible a large scheme can actually be.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email enquiries@sharpepritchard.co.uk.
Sign up for more legal updates
[1] Hillside Parks Limited v Snowdonia National Park Authority [2020] EWCA Civ 1440
[2] R (Fiske) v Test Valley Borough Council [2023] EWCA Civ 1495
[3] R (Dennis) v LB Southwark [2024] EWHC 57 (Admin)
[4] Finney v Welsh Ministers & Ors [2019] EWCA Civ 1868
[5] The new section 73B is not proposed to cover section 73 permissions